Brighton & Hove City Council

Brighton & Hove City Council: the register

Ruling 24 017 530

Folio 136

Finding: Fault found

Go to the remedies

Finding recorded by the ombudsman
Upheld
Service
Housing: Homelessness
Council
Brighton & Hove City Council
Body
Local Government and Social Care Ombudsman
Decided
Summary
Ms Y complained the Council failed to complete work to repair significant damp issues at her property. We find the Council at fault for a delay in completing the necessary work to repair Ms Y’s property. This has caused Ms Y distress, frustration and uncertainty. The Council has agreed to apologise, make a symbolic payment and complete service improvements to remedy the injustice caused.
Summary as published by the Local Government and Social Care Ombudsman.

Remedies

Words in quotation marks are quoted from the ombudsman’s decision.

States worked out on 9 October 2026.

The ombudsman publishes no entry for a remedy.

Remedies ordered in ruling 24 017 530, and the entry that the ombudsman publishes for each
Ordered Outcome publishedThe ombudsman publishes no entry for a remedy.
No. What was ordered Deadline Payment Date Entry Payment
1 ApologyApologise to Ms Y for the injustice caused by the delay in completing the repair works to the property.Deadline as worded: Within one month of the final decision Deadline passed 19 November 2025. Outcome not published. None No outcome published by the ombudsman
2 PaymentMake a symbolic payment of £1800 in recognition of the injustice caused by the faults identified.Deadline as worded: Within one month of the final decision Deadline passed 19 November 2025. Outcome not published. £1,800.00 No outcome published by the ombudsman
3 PaymentOffer to pay Ms Y the financial remedy of £640 which was offered in the stage two complaint response.Deadline as worded: Within one month of the final decision Deadline passed 19 November 2025. Outcome not published. £640.00 No outcome published by the ombudsman
4 Action for the personConsider whether, under section 2.2 of the tenancy agreement, it considers Ms Y’s property was habitable following the contractors report in April 2024. If the Council considers Ms Y’s property was not habitable it should offer to reduce Ms Y’s rent for the period between April 2023 and May 2025.Deadline as worded: Within one month of the final decision Deadline passed 19 November 2025. Outcome not published. None No outcome published by the ombudsman
5 Service changeIssue guidance to its complaints team on how to correctly signpost housing complaints to the correct Ombudsman.Deadline as worded: Within three months of the final decision Deadline passed 19 January 2026. Outcome not published. None No outcome published by the ombudsman
6 Service changeEnsure it has a process in place to monitor when there are delays in planned works being completed. The process should ensure the Council can follow up on any delays and ensure necessary works are completed within a reasonable timeframe.Deadline as worded: Within three months of the final decision Deadline passed 19 January 2026. Outcome not published. None No outcome published by the ombudsman
Stated payments ordered £2,440.00 Outcomes published by the ombudsman: none